How to Plan the First Replacement Fabrics for a Lightweight Containerboard Machine
Plan the first replacement forming fabrics, press felts, and dryer fabrics for a lightweight containerboard machine with a position-by-position RFQ checklist.
Before commissioning a lightweight containerboard machine, create a spare clothing register for every forming fabric, press felt, and dryer fabric position. Reserve stock or supplier capacity for critical positions with long lead times. Use early production records to confirm specifications for positions where the commissioning setup may change.
What the Lucca PM3 project illustrates
DS Smith’s Lucca mill in Porcari, Italy, planned PM3 for lightweight containerboard. The project scope included new stock preparation and the retirement of PM1. At its November 3, 2026 Capital Markets Day, DS Smith reported that structural installation and the start of stock preparation operations had been completed in the third quarter. Mechanical, electrical, and control-system installation or commissioning was still in progress at the time of the presentation, which listed paper-machine startup for the fourth quarter of 2026. DS Smith Lucca mill profile · DS Smith Capital Markets Day presentation, p. 38
The schedule describes the plan as disclosed on November 3. The checklist below is for mill teams planning their own replacement clothing.

Build the spare clothing register by machine position
Give each position its own record before the machine starts. Capture the machine ID, position tag, confirmed dimensions, installed clothing reference, drawing revision, installation window, and supplier lead time. Where a new machine replaces an older one, keep inventory records by machine and verify the fit of any spare considered for transfer.
| Machine section | What to confirm before requesting a quote |
|---|---|
| Forming | Former configuration and fabric position, running dimensions, current construction if known, target grades and basis-weight range. Huatao forming fabrics |
| Press | Exact press position, felt dimensions, installation access, endless or seamed configuration, and dewatering requirements. Huatao press felts |
| Drying | Dryer group and position, dimensions, seam type, and required air permeability with the applicable test method or units. Huatao dryer fabrics |
Prioritize positions where a clothing failure would stop production and a replacement could arrive after the next available installation window. For positions with open specifications, ask suppliers which parameters they need to quote and the latest date those parameters can be confirmed.
Review the first changeouts before finalizing repeat orders
Once production stabilizes, record the running grade, basis weight, speed, clothing age, quality trends, and reason for each early changeout. Use section-specific measurements where available, such as forming-section drainage and sheet formation, press outlet dryness, or dryer-section moisture profile. Record the operating settings alongside the measurements so the team can compare like conditions.
An early changeout during troubleshooting provides a different basis for a repeat order than a changeout after sustained production. Record whether the clothing was removed during a planned stop, following installation damage, or after a measured decline in performance. Use those records to decide whether to repeat the installed specification or trial an alternative at a defined position.
What to include in the first replacement RFQ
- Machine ID, installation position, and drawing revision.
- Confirmed length and width, plus construction or seam details as applicable.
- Running grades, basis-weight range, and operating speed.
- Installed clothing reference and any issue the replacement needs to address.
- Required quantity, delivery date, and installation window.
- Open parameters, the person responsible for confirmation, and the confirmation deadline.
Send one specification sheet per position. If a trial is needed, agree on the comparison grade, operating conditions, and acceptance criteria before installation.