What to Check Before Ordering a Forming Fabric for a Short Shutdown

Before ordering a replacement forming fabric, verify machine fit, installation access, handling, and delivery for a short paper machine shutdown.

When a paper machine has only a few hours of planned downtime, confirm three things before ordering a replacement forming fabric: the exact fabric position and specification, the installation route and handling requirements, and the latest arrival date that leaves time for inspection. Put all three in the request for quotation (RFQ) so the supplier can review the same requirements as the mill.

Checklist showing fabric position verification, installation route review, and receiving inspection before a planned shutdown.
Three checks before ordering a replacement forming fabric for a short shutdown.

Verify the fabric against the machine position

Ask the process team to confirm the machine ID, former type, and exact position. Where the former uses separate top and bottom fabrics, identify which one is being replaced. Use the installed fabric ID and the latest approved specification or drawing revision as references. Confirm the required finished length and width, construction, and any applicable permeability requirement, including its test method and units. If a reference or measurement differs between records, resolve the discrepancy before approving the order.

For a repeat order, record any changes to the former or fabric path since the previous installation. If the quote proposes a different construction, have production and maintenance review the application and installation requirements before approving it. Keep the existing approved configuration as the purchasing baseline while any proposed change is being evaluated.

Verify the installation route before agreeing to packaging

Have maintenance confirm how the packed fabric will travel from receiving to the machine and how the crew will position it for the mill’s approved installation method. Check access, staging space, available lifting or handling equipment, and any limits that affect package size or orientation. Ask the supplier for package dimensions, gross weight, handling instructions, and any applicable orientation markings.

Agree in advance how the crew will protect the fabric from creasing during storage, handling, and installation. Review the method with the mill and supplier against the actual space, equipment, and fabric position. Record the time available for the fabric change within the overall shutdown, allowing for other jobs and the mill’s restart checks.

Set a delivery date that leaves time for inspection

Work backward from the shutdown to establish the latest acceptable delivery date. Allow time to check the delivered fabric against the purchase order, verify identification and packing condition, and resolve any discrepancies. Agree with the supplier on which checks the receiving team can perform without disturbing protective packaging and how it should report damage or identification errors.

Ask for separate dates for technical approval, dispatch, and arrival at the mill. Identify who will confirm that the correct fabric is on site and ready before the outage plan is finalized.

Forming fabric RFQ checklist

OwnerConfirm before placing the order
Production or process engineeringMachine ID, former type, fabric position, installed fabric ID, approved specification revision, finished dimensions, construction, applicable permeability requirement, and usual grades and speeds.
MaintenanceApproved installation method, handling and access constraints, equipment availability, package orientation, crease protection, and the time allocated for the change.
Purchasing and receivingQuantity, package details, technical approval date, required arrival date, receiving inspection window, and contacts for resolving discrepancies.

Send one RFQ sheet per fabric position. Ask the supplier to identify any open dimensions, installation constraints, or delivery assumptions in its quote. For product inquiries, share the approved position specification and shutdown dates with the Huatao team. Huatao forming fabrics